FEASIBILITY OF SWAT ROAD PROJECT FOR HYDRAULICS & HYDROLOGICAL ASSESSMENT The purpose of this report is to describe and justify the drainage system and stormwater system.The Upper road site...
Naval Anchorage, Karachi “Town Planning and Designing of Infrastructure Development Works of PNWT” Project Description: The project site is located at Super Highway (M-9 Motorway Karachi. The climate of...
Urban Surface Flood Modelling of Korang River Salient Analysis Design Flood 6500 cumecs Design Flood (Safety) 8000 cumecs Spillway Capacity 8000 cumecs Study Reach 25 km Slope 0.0006
Dam Break Modelling of Lisanjala Project Salient Features Dam Concrete Gravity Dam Catchment Area 15.060 Sq.km Design Flood 537.70 cumecs Design Flood (Safety) 695.60 cumecs Spillway Type Ogee with...
Dam Break Modelling of Asritkadam Hydropower Project Salient Features Installed Capacity 229 MW Catchment Area 2213 Sq km Discharge 130 Cumecs Dam Concrete Gravity Dam Headrace Tunnel 10,291m...